Approval of details

Permission granted is not permission to build. More than half of London's condition sign-offs miss the 8-week deadline.

Most planning permissions come with conditions: drainage, construction logistics, materials, cycle stores. Many must be signed off before work can start. We analysed 17,079 applications to discharge conditions on London housing schemes, submitted 2021–2025.

House London #0 · Insight brief · Source: PlanIt-derived London planning applications extract (fetched Aug 2026)

54%of decided discharge applications took longer than the 8-week statutory period
60days: median time to a decision. One in four took over 106 days
11%took more than six months (26 weeks)
16recorded deemed discharges, all in 3 boroughs, against roughly 8,300 late decisions

1 · The clock

Councils work to the deadline, and a long tail sits behind it

Councils have eight weeks to decide an application to approve details required by a condition (Development Management Procedure Order 2015, article 27). 22% of all decisions land in the final week before that deadline. After it passes, nothing forces a decision, and the queue thins out slowly over months.

Discharge applications by weeks to decision

Within 8 weeksAfter 8 weeks
Residential discharge-of-condition applications submitted 2021–2025 and decided (approved, refused or split). Withdrawn and undecided applications excluded. The final bar groups everything over 26 weeks.

2 · Getting better, slowly

The late share has fallen since 2021, but it has stalled at about half

Applications submitted in 2021 came out of a pandemic backlog. Since 2024 the share decided late has sat around half.

Share of applications decided after 8 weeks, by year submitted

Undecided applications more than 8 weeks old at the end of the extract count as late. Dashed line marks 50%.

3 · Bundling

Applications that bundle many conditions are the slowest and most often refused

One application can ask for several conditions to be signed off at once. With seven or more, 85% are decided late, the median wait is 104 days, and 29% are refused or only partly approved. A single refused item sends the whole package back.

Share decided after 8 weeks, by number of conditions in the application

Conditions in one applicationApplicationsMedian daysRefused or part-refusedDecided after 8 weeks
Condition count read from the application description (e.g. “conditions 3, 5, 6 and 11”). Larger schemes tend to bundle more, so scheme size explains part of this.

4 · What gets stuck

Drainage is both slow and often refused

Read by Jev, which looks only at the conditions being signed off, drainage plans are decided late 63% of the time and refused 22% of the time. Construction logistics plans run just as late (63%) but are refused less often (16%) than keyword matching suggested. Both are usually needed before work can start. Fire safety details (23%) and cycle and refuse stores (21%) are refused most often.

Condition topics: share decided after 8 weeks

Jev: conditions being signed offKeyword tagger: whole description
Sorted by Jev's share late. Values at right are the share refused or part-refused, Jev first. The keyword tagger reads the whole description, which usually repeats the original permission, so it over-counts some topics: 12,594 applications tagged for waste, cycle and parking, against 2,922 by Jev. An application can cover several topics. Topics with at least 200 applications by either method shown.

5 · Over a scheme's life

Major schemes come back for condition sign-offs about seven times on average

We matched discharge applications to 1,460 permissions granted 2021–2023, giving each at least two and a half years to come back. Developers take their own time too: the median first submission comes 181 days after permission. When a discharge is refused and resubmitted, the approval comes a median 69 days after the refusal (378 matched pairs).

Condition sign-offs per permission, by scheme size

Scheme sizePermissionsHomesDischarge applications (mean)With a refused dischargeDays from permission to first submission (median)Days from permission to last decision (median)
Only permissions that appear in the extract and could be matched by reference number. Strategic schemes are a small sample. Scheme size read from descriptions; “Unknown” is mostly householder-scale and conversion work.

6 · Boroughs

Practice varies more than speed

The share decided late runs from about 40% in Enfield to 71% in Bexley. Refusal practice varies far more: Camden and Wandsworth almost never refuse a discharge, while Croydon refuses or part-refuses over a third. A refusal is fast for the council but costs the applicant another round.

Boroughs with at least 300 discharge applications in the extract

BoroughApplicationsMedian daysRefused or part-refusedDecided after 8 weeks
18 boroughs are too thinly covered in the extract to compare, including Barnet, Tower Hamlets, Westminster, Newham and Hackney.

What could change

Four levers the data points to

Make deemed discharge real

Since 2015, applicants can serve notice that many conditions are treated as approved once the deadline passes. The extract records only 16 deemed discharges against about 8,300 late decisions, 13 of them in Croydon. Only 3 of 28 boroughs record any, so the route is either almost unused or invisible in most council systems. Either way, nobody can tell how often applicants use it. Recording it consistently would be the first step.

Standard London conditions

Construction logistics, drainage and cycle/refuse storage come up thousands of times. London-wide standard wording and templates would cut both refusals and back-and-forth.

Fewer pre-start conditions

Applications bundling seven or more conditions are late 85% of the time. Settling drainage and logistics detail at the application stage for larger schemes would shorten the queue after permission.

Publish the clock

Discharge decisions get far less scrutiny than the headline speed figures for planning applications. Boroughs already hold these dates, so a quarterly table would cost little.

Method and caveats