Conditions Queue Models
— of London's condition sign-offs miss the 8-week deadline, and many have to be cleared before building can start. These models predict, on the day an application arrives, whether it will be late and how long it will take. The best, —, scores an AUC of — against — for the borough average. Reading the description is what lifts it: without it the model scores —. Decision time can't be predicted to the day, because most decisions land near the deadline, but the slow tail can be flagged.
Why predict this?
The problem
Planning permission usually comes with conditions: drainage, construction logistics, materials. Many must be signed off before work can start. Councils have 8 weeks to decide each sign-off, and more than half take longer. The delay comes after the scheme has already been approved, so it holds up homes that are otherwise ready to go.
Who the prediction helps
Councils can flag high-risk sign-offs on the day they arrive and give them early officer time. Developers can plan start dates around a realistic sign-off date rather than the statutory one. Policy teams can see which features of an application, such as bundling many conditions, are linked to delay.
What counts as useful
The bar is the borough average: knowing only which council decides already tells you something. A model is worth using if it sorts applications into clearly higher- and lower-risk groups than that. It won't be right about every application, so it suits triage and planning ranges, not promises.
Will a sign-off be late?
Models trained on 2021–23 submissions and tested on 2024–25, using only what is known on the day an application is submitted. AUC measures how well a model ranks applications from most to least likely to be late.
Model scores
AUC on the 2024–25 test set. Bars start at 0.5, a coin flip. The best model is highlighted.
How often each risk group was actually late
Test applications split into ten equal groups by LightGBM's predicted risk.
Does the description help?
Every model fitted three ways on the same applications: with no description features, with the keyword tagger's, and with Jev's. Bars start at 0.5, a coin flip. AUC is shown for the two late models and C-index for the three decision-time models.
Score by description features used
The description lifts every model. Jev's labels, which read only the conditions being signed off, do best in all five.
Average error in days barely moves
The description helps put applications in the right order, not predict the exact number of days.
| Description features | Model | Average error (days) | Change |
|---|
How long will it take?
Exact days can't be predicted much better than each borough's median, because most decisions land close to the 8-week deadline. The useful outputs are the order of applications, from quickest to slowest, and a "plan for" range.
What is being predicted
- Target
days: days from submission (start_date) to decision (decided_date).- Still undecided
- Days so far, up to when the data was fetched, marked as not yet decided. The survival model treats these as "at least this long".
- Models
- Ridge and LightGBM predict log(1 + days); the Cox survival model predicts the daily chance of a decision; the quantile models give P50 (typical) and P90 (plan for).
- Tested on
- 2024–25 decisions, trained on 2021–23.
How close the predictions are
Decided 2024–25 applications. Rank correlation: 1 = perfect order, 0 = none. The borough median is closest in days; the models order applications slightly better.
| Prediction | Median error (days) | Within 2 weeks | Within 4 weeks | Rank correlation |
|---|
Predicted vs actual days
2024–25 decisions split into ten equal groups by predicted time (P50). The actual median sits near day 56 for most groups and rises only for the slowest-predicted ones. Predictions run high because 2021–23, the training years, were slower.
Days-to-decision scores
Higher C-index is better, lower MAE is better. A dash means the score doesn't apply to that model.
| Model | C-index | MAE (days) | AUC (late) |
|---|
Typical and "plan for" times by conditions bundled
Median predicted P50 and P90 for decided test applications, with the actual median.
What drives it, across all five models
Each feature is shuffled in the test set and the drop in each model's score is turned into a share of 100%. The two late models and three days models largely agree. Switch to see the same ranking with JEV reading the descriptions.
Average share of importance
Top 12 features, averaged over the five models. Each label ends with its column name in brackets; the data dictionary defines them.
Share of importance by model (%)
Darker cells mean the model relies on that feature more.
| Feature | Late · logistic | Late · LightGBM | Days · ridge | Days · LightGBM | Days · Cox |
|---|
Bundling conditions
Holding each application's borough, size and topics as they were, and changing only the number of conditions bundled, shows bundling is linked to lateness in its own right.
Predicted chance of being late, all else equal
Logistic regression on the test set, using the keyword count and JEV's count. Rings show how often applications with that JEV count were actually late.
What speeds decisions up or slows them down
Cox model speed ratios with 95% ranges. Below 1 is slower. Boroughs compare with Croydon and application sizes with Small; numeric features are per standard deviation. Column names are in brackets.
Reading the descriptions with JEV
A description has two parts: the request ("condition 13 (construction method statement)") and a copy of the original permission. The keyword tagger reads both, so it often tags the scheme. Jev, TypeSafe's decision model on OpenRouter, answers yes/no and multiple-choice questions about only the conditions requested. It labelled — of the modelled applications.
Share of applications tagged with each topic
A long gap means the keyword tagger is mostly picking the topic up from the copied scheme text.
Late model with each set of description features
Same applications and split. LightGBM is averaged over 5 seeds.
| Description features | Logistic AUC | LightGBM AUC | ± seeds |
|---|
All five models, keyword vs JEV
C-index for every model, and AUC for the two late models.
| Model | C-index, keyword | C-index, JEV | AUC, keyword | AUC, JEV |
|---|
External data tested
Two sources from the team's Data Asset Register were joined and tested on the same split. Neither helped: area-level data mostly repeats what the borough already tells the model.
With and without each source
LightGBM late AUC and days C-index. House prices act as a disguised date stamp and make both slightly worse.
| Features | Source | Late AUC | Days C-index |
|---|
Site constraints within the same borough
Late share with and without each constraint, and the difference when compared inside each borough.
| Constraint | Late, with (%) | Late, without (%) | Within-borough difference (points) | Boroughs |
|---|
Definitions, method and what's left out
- Late
- Decided more than 56 days (8 weeks) after submission, or still undecided past that point when the data was fetched in August 2026.
- AUC
- How well a model ranks applications from most to least likely to be late. 0.5 is a coin flip, 1 is perfect.
- C-index
- The share of application pairs a model puts in the right order of time taken. Undecided applications count as "at least this long".
- P50 and P90
- Quantile predictions: the typical time, and the time by which about nine in ten should be decided.
- Speed ratio
- From the Cox survival model: how much a feature changes the daily chance of getting a decision. Below 1 is slower.
- Keyword features
- Topics, number of conditions and pre-start flag found by keyword matching on the whole description (
conditions_queue.analysis). - JEV features
- The same, labelled by Jev (~typesafe/jev-latest, OpenRouter's decisions API) from the request part only: a probability per topic, kept at 0.5 or more (
conditions_queue.classify_jev). - Importance
- Permutation importance: the drop in each model's test score when a feature is shuffled, as a share of all drops.
Where the numbers come from
- Data
- PlanIt-derived London planning applications extract, discharge-of-condition applications submitted 2021–2025.
- Notebooks
- 02_late_model.ipynb and 03_days_model.ipynb, exported by
conditions_queue.build_dashboard_dataintodata/ui_dashboard.json. This page is a fixed copy of their results. - Data dictionary
- docs/DATA_DICTIONARY.md defines every column, target, feature and table used here.
What's left out
- Causes
- These are associations. Applicants who bundle may differ in ways the data doesn't record.
- Case detail
- Consultee responses, extensions of time and validation dates aren't in the data and are likely the biggest missing drivers.
- Application size
- The
app_sizecolumn: PlanIt's Small/Medium/Large label. It tracks the size of the scheme (Large: median 135 homes, Medium: 22, Small: 7) and is the strongest single predictor. Exactly how PlanIt assigns it hasn't been confirmed from its documentation. - Flood zones
- Not tested: the national file is 2.5 GB.